National5 delivery years4 regionsReviewed

The PJM capacity auction: what it is, what it cost your bill and what to watch next

Every year PJM sets what plants are paid to be ready on the hottest and coldest days. That cost reaches homes in Pennsylvania, Ohio, New Jersey and northern Illinois. Here are the results, the dates and your options.

See my plansPartner toolFree, no obligation. We may earn a fee if you sign up.
Published 7 min readBy The Day Company review team · How we verify figures
$333.44PJM's 2027/28 capacity price per megawatt-day, set at the cap
$175 to $325The floor and cap PJM uses, extended through 2029/30 (PJM, Apr. 30, 2026)
Short answer

PJM's capacity auction sets what the grid pays plants to be ready at peak. The latest result, for 2028/29, hit the $325 cap (PJM, July 14, 2026). June 2027 bills use the 2027/28 price, about 1.3% above last year's. The next auction closes Dec. 15, 2026.

What do you need right now?
Compare plans at my ZIP

Partner tool A partner runs the plan finder. If you sign up, it may pay us a fee. We do not take payment to change a score, a rank, the order of our rankings, or what we write about a company. Paid links and partner tools are always labeled as paid.

The next PJM auction closes Dec. 15, 2026, and PJM's schedule lists results on Dec. 22, 2026. Confirm the date on PJM's site. We update this page that day.
$333.44PJM's 2027/28 capacity price per megawatt-day, set at the cap
$175 to $325The floor and cap PJM uses, extended through 2029/30 (PJM, Apr. 30, 2026)
June 1, 2027The day the 2027/28 capacity price starts to apply
Dec. 15, 2026The day the next auction, for 2029/30, closes

The 4 things to know

  • Capacity is one part of supply. PJM says it is a relatively small part of a retail bill. Energy, wires and taxes are the rest.
  • The cap slows the rise, it does not end it. Three auctions in a row now sit at or near the cap.
  • Each state feels it its own way. Pennsylvania and Ohio reset prices to compare on set dates. New Jersey buys in a yearly state auction.
  • Ameren Illinois is not in PJM. It is in a different grid group, MISO. See why an Ameren bill is high.

Built on public data from PJM Interconnection, the Pennsylvania Public Utility Commission, the New Jersey Board of Public Utilities and the Citizens Utility Board. Auction results and dates read Nov. 13, 2026.

01 · The auction

What is the PJM capacity auction?

PJM runs the power grid for 13 states and Washington, D.C. Each year it holds an auction called the Base Residual Auction. In it, plants and other resources bid to be on call for a future year, which runs June 1 to May 31. The price is in dollars per megawatt-day.

The price that clears is paid by the companies that sell power. They pass it on. That is why it shows up in your supply price, not your delivery charge.

02 · Results

What did the auctions pay?

Look at the jump. In 2024/25 most of PJM paid $28.92. A year later it was $269.92. Then it hit the cap.

PJM capacity auction results, dollars per megawatt-day (read Nov. 13, 2026)
Delivery yearPriceFloor and capWhat happened
2024/25$28.92NoneMost of PJM. Baltimore area (BGE) and some other zones cleared higher (PJM 2024/25 report)
2025/26$269.92NoneMost of PJM. Two zones cleared higher: Baltimore area (BGE) $466.35 and Dominion area $444.26
2026/27$329.17Floor $177.24, cap $329.17Cleared at the cap
2027/28$333.44Floor $179.55, cap $333.44Cleared at the cap, 6,623 megawatts short of the target
2028/29$325.00Floor $175, cap $325Cleared at the cap, 6,831 megawatts short
2029/30Results due Dec. 22, 2026Same collar appliesNot held yet
Capacity price by delivery year, dollars per megawatt-day
2024/25
$28.92
2025/26
$269.92
2026/27
$329.17
2027/28
$333.44
2028/29
$325.00

The cap and floor are PJM's price collar. FERC approved it for the 2026/27 and 2027/28 auctions and, on Apr. 28, 2026, for 2028/29 and 2029/30 (PJM, Apr. 30, 2026).

"Short" means PJM bought fewer megawatts than its own target for a safe grid. In both of the last two auctions the price sat at the cap while supply fell short.

03 · Bill effects

What did it do to supply prices and bills?

Capacity is not the only cause of any one bill rise. Regulators rarely split it out. These are the rises each one reported, and what it said about the cause. We found no Ohio regulator source that ties a rise to capacity, so Ohio is not in the table.

What each source reported
AreaWhat the source reportedSource and date
PennsylvaniaTypical price to compare rose 5% to 16% on June 1, 2025. The PUC named natural gas prices and "higher capacity costs"PA PUC, June 2, 2025
ComEd (northern Illinois)PJM's price was 22% higher for ComEd's area. ComEd's whole-year estimate: about 12% more on average, June 2026 to May 2027CUB (consumer watchdog), June 10, 2026
New JerseyTypical bills were projected up 17.23% to 20.20% in June 2025. In June 2026 the change was about -1.8% to +1.6%, before state bill creditsNJ BPU, 2025 and Feb. 12, 2026

The June 2025 rises are the big ones, because that was the first year at the high price. The next jump was small because the price was already near the cap. For the details, see our guides for Pennsylvania, New Jersey, Ohio and ComEd.

04 · June 2027

Why will June 2027 bills look like this?

On June 1, 2027, the 2027/28 capacity price of $333.44 starts. It is only about 1.3% above 2026/27, so capacity alone should add little. That is a cap at work.

Your own supply price can still move. In Pennsylvania and Ohio, your utility resets its price to compare on set dates. In New Jersey, the state's yearly supply auction (BGS) sets June prices, and its yearly auction is usually held each February (NJ BPU). Check your utility's price on its state page.

  1. Dec. 15, 2026The auction for the 2029/30 delivery year closes.
  2. Dec. 22, 2026PJM's schedule lists the results for this date. Confirm on PJM.
  3. Feb. 2027New Jersey's yearly supply auction is usually held in February, setting June 1 prices.
  4. May 2027PJM's next window opens, for the 2030/31 auction.
  5. June 1, 2027The 2027/28 capacity price starts. Many utility prices reset the same day.
05 · December

What should you watch in December?

The December auction is for the 2029/30 year, so it shapes bills from June 2029. Four signs tell you if the cap is working. One filing is also pending. PJM asked FERC on Oct. 29, 2026 to start a Reliability Backstop Procurement on March 1, 2027. It aims at the roughly 6,800 megawatt shortfall from the 2028/29 auction, and PJM wants the cost to fall on large loads. FERC accepted the first filing on Sept. 29 and paused it, so this one needs FERC's go-ahead (PJM, Oct. 29, 2026).

  • The price lands under the cap. That means supply is catching up.
  • New plants clear in the auction. That is supply you will not have to pay a high price for.
  • The price lands at the cap again. That means demand is still ahead of supply.
  • The shortfall grows past 6,831 megawatts. That is a gap the cap cannot hide.
06 · Your move

What can a household do?

You cannot bid in the auction, but you can pick how you buy supply. If your state lets you choose a seller, a fixed price held past May 2027 hides a utility price reset. Shopping in Pennsylvania? Start with the price to compare. See our fixed rate guide and compare to your utility's price to compare first. If you use less power at peak, you also cut what capacity costs you. See how to lower your electric bill.

Where your state allows it, compare plans side by side:

07 · The map

Which states are in PJM?

PJM covers all or part of 13 states and D.C. Our five choice states differ.

Where the PJM price reaches
StateIn PJM?Start here
PennsylvaniaYesPrice to compare
OhioYesOhio electricity rates
New JerseyYesNew Jersey electric rates
IllinoisComEd area only; Ameren is in MISOComEd rate reset
TexasNo, it runs its own grid (ERCOT)Texas guides
Your next step

Check your utility's price to compare and its end date, then test a fixed offer that runs past May 2027 against it.

Compare plans at my ZIP

Partner tool A partner runs the plan finder. If you sign up, it may pay us a fee. We do not take payment to change a score, a rank, the order of our rankings, or what we write about a company. Paid links and partner tools are always labeled as paid.

Read nextMonthly electricity report Read it
08 · Quick answers

Questions, answered

What is a PJM capacity auction?

It is a yearly auction where PJM buys the promise of power for a future year, June 1 to May 31. The price clears in dollars per megawatt-day, and the cost passes to the companies that sell you power.

What was the last PJM capacity auction price?

The 2028/29 auction, held in July 2026, cleared at the $325 per megawatt-day cap (PJM, July 14, 2026). The 2027/28 auction cleared at $333.44.

Why are electric bills going up?

In PJM states, higher capacity prices are one named cause, alongside gas prices and wires costs. For your own bill, read Pennsylvania, New Jersey or Ohio.

What is the PJM price cap?

It is a limit on the auction price. PJM's version has a cap near $325 and a floor near $175 per megawatt-day. FERC approved it for 2026/27 and 2027/28 and, on Apr. 28, 2026, for 2028/29 and 2029/30.

When is the next PJM capacity auction?

The 2029/30 auction closes Dec. 15, 2026. PJM's schedule lists results on Dec. 22, 2026. Confirm the date on PJM's site.

Will my June 2027 bill go up?

Capacity alone should add little, since 2027/28 is about 1.3% above 2026/27. Your supply price can still change on its own date. Check your utility's price to compare.

Does Ameren Illinois use the PJM price?

No. Ameren Illinois is in MISO, a different grid group. Read why an Ameren bill is high.

Can I avoid the capacity price?

Not fully. Every supplier pays it. A fixed rate plan can hold your supply price steady for a term, and using less power at peak lowers your share.

Where to next

What do you want to do next?

Sources

Sources and updates

Sources (13)
Changelog · 1 update, newest November 13, 2026
  • November 13, 2026: Guide published.

How to cite this page: The Day Company, "The PJM capacity auction: what it is, what it cost your bill and what to watch next", updated November 13, 2026, https://theday.company/switch/pjm-capacity-auction-electric-bills.

Reviewed is the last day a person re-checked every number on this page.

The Day Company is not affiliated with PJM, any regulator, utility or supplier named here. Auction results and bill effects come from the public records and dates shown and can change. This is general information, not a quote, an offer, legal advice or a promise of savings. Our plan finder is Power HQ, operated by Blitz Ventures Inc. (doing business as EnergyBot). It shows plans only in Texas, Pennsylvania, Ohio, New Jersey and Illinois, where it holds Pennsylvania Public Utility Commission licence A-2018-2647582, Public Utilities Commission of Ohio licence 18-1282E, New Jersey Board of Public Utilities licence EA-0519 and Illinois Commerce Commission licence 17-0994, and is a registered broker with the Public Utility Commission of Texas.