Is there a New Jersey battery rebate in 2026?
Not statewide. New Jersey has no open statewide program that pays you for a home battery. The state's home battery program, part of the Garden State Energy Storage Program, is still a staff proposal. It is planned to open by July 2027.
Two utilities pay now. PSE&G takes $5,000 off a new battery through its GridSmart pilot. JCP&L pays people who already have a battery for letting it help the grid in summer.
| Utility | Program | Money | The catch |
|---|---|---|---|
| PSE&G | GridSmart Battery Program | $5,000 off a new battery, plus up to $25,000 interest-free on your bill | PSE&G can use the battery for 7 years; pay back part of the $5,000 if you leave before year 5 |
| JCP&L | Energy Saving Rewards | About $360 a summer for the average customer | Tesla and Enphase batteries only; program period ends June 30, 2027 |
| Atlantic City Electric | None for batteries | None | Its rewards program covers smart thermostats only |
| Rockland Electric | None for batteries | None | Its New Jersey program covers thermostats only |
| Statewide (all four utilities) | Garden State Energy Storage Program, home block | Proposed: up to $200 per kW a year for 10 years | Not open; planned by July 2027; new batteries only |
Town-run utilities are not part of these programs. The rest of this page goes program by program. First: the tax breaks most people ask about.
Which tax breaks are left for a New Jersey battery?
The 30% federal credit is gone for new batteries. The IRS says it is "not available for any property placed in service after December 31, 2025." The cost counts on the day the install is finished, not the day you paid.
Paid a deposit in 2025 but the battery went in after New Year's? The credit is likely $0. The IRS counts the day the install was finished. Ask a tax pro about your own case.
New Jersey has one tax break that can help, and one that does not.
- Sales tax: the state exempts solar energy devices, and its rule names devices "for storing solar generated energy." Give the seller Form ST-4.
- Federal credit: still yours if the install was finished by Dec. 31, 2025.
- Battery charged only from the grid: the sales tax rule does not clearly cover it.
- Property tax: New Jersey's renewable energy exemption lists systems that make power. Batteries are not on the list.
- Leased batteries: the company that owns one may still claim a business credit. You see that only in the lease price.
The BPU's own cost math for the state program assumes companies that own home batteries still claim a 30% business credit. That is not a credit you claim yourself.
What does my utility pay?
Pick your utility and where you are with a battery. The finder lists every program we found for you, what it pays up front and over time, and the catch in each one.
Pick your utility and where you are with a battery. The answer lists every program we found for you, what it pays up front and each year, and the catch.
Partner toolWe get paid if you sign up. You don’t pay more, and it never changes our scores.
The amounts come from each program's own page and the BPU's filings on Oct. 26, 2026. The 10-year numbers assume a program keeps paying the same amount. The state program's numbers are a proposal, not a promise.
Every home on the four big utilities can also pick who sells its power. That choice does not change the battery money, but it can change your bill.
What does PSE&G's GridSmart program pay?
PSE&G takes $5,000 off a new battery, right on the installer's bill. It also lends up to $25,000 with no interest, paid back on your PSE&G bill. PSE&G announced the pilot on Aug. 26, 2026, and says spots are limited.
You need a smart meter, Wi-Fi and 12 months of PSE&G bills. The battery must be a Tesla Powerwall 3, an Enphase 10C, or two or more Enphase 5P units. PSE&G's FAQ asks for at least "8.5 kW of storage capacity." PSE&G sends an email at least 1 hour before an event.
The biggest catch is leaving early. Drop out before year 5 and you pay back part of the $5,000.
From PSE&G's GridSmart terms. Any loan balance on your bill also comes due when you leave.
Selling your home in the next five years? Ask PSE&G how the program moves to a buyer before you sign. Our PSE&G rates guide covers what you pay for power.
What does JCP&L pay battery owners?
JCP&L pays people who already have a battery. You let it draw from the battery at peak times in summer, and it pays you for each summer. JCP&L says its average customer earns $360 a summer, paid on a virtual prepaid Visa card.
Any Tesla Powerwall 2, 3 or + or Enphase IQ battery can join, old or new. You do not need solar. JCP&L will not call an event when a severe storm is forecast. You can leave any time. The program period runs from June 1, 2025 to June 30, 2027.
JCP&L's page says it pays "$100 per average kW performed" each summer. Its own FAQ example pays $360 for 6 kW, which is $60 per kW. We use the $360 figure, which JCP&L also gives for its average customer. Ask JCP&L which rate applies before you count on it.
JCP&L runs the program with a company called EnergyHub. Our JCP&L rates guide covers your supply price.
What about Atlantic City Electric and Rockland Electric?
Neither had a home battery program on Oct. 26, 2026. Atlantic City Electric's Energy Wise Rewards pays for smart thermostats only, up to $100. Rockland Electric listed only a thermostat program for New Jersey homes at a BPU meeting on July 30, 2026. Its battery program is for its New York side.
For these homes, the state program is the one to watch. It sets aside 21 MW for Atlantic City Electric and 4 MW for Rockland Electric. Our Rockland Electric guide covers that utility's price.
What is the Garden State Energy Storage Program?
It is the state's battery program. Phase 1 pays for big batteries on the grid, not homes. Phase 2 starts with a home block, and the BPU staff proposed it on Aug. 17, 2026. The board has not voted on it yet.
Here is the catch, in the BPU's own example. A 13.5 kWh, 11.5 kW battery could earn up to $2,300 a year at $200 per kW. But the pay is cut by a "Performance Factor" based on how much power the battery gives during events. In the BPU's example that factor is 23.5%, so the battery earns $540 a year. Over 10 years that is about $5,400, by our math.
Split by each utility's share of home power sales. When a utility's share fills up, new homes go on a waitlist.
More rules from the proposal: new batteries only, with no older or expanded systems. A $50 application fee you do not get back. The battery must be running within 12 months of approval. A company that owns or runs your battery must pass at least 70% of the pay to you. And homes on a supplier plan that passes wholesale costs through cannot join.
- Proposal publishedAug. 17, 2026. Public comments closed Sept. 10, 2026.
- Board order plannedPlanned for October 2026. It was not on the Oct. 14 or Oct. 28 meeting agendas.
- Utility filingsPlanned for December 2026, after the board order.
- Program opensPlanned by July 2027.
- 50 MW installedTarget: July 2028. The full 150 MW by February 2030.
Once it opens, the BPU staff say it "will be the only residential storage incentive available" for new batteries. The utility programs from the current cycle run until then. A separate July 15, 2026 proposal would add programs for batteries people already own, from 2027 to 2029.
Should I buy a battery now or wait for the state program?
It depends on your utility and how soon you need backup. In the PSE&G area, $5,000 now is close to the state program's 10-year example of about $5,400. And the PSE&G money comes up front.
The state program is a proposal. JCP&L's program period ends June 30, 2027. Money paid later is worth less than money paid now.
The two do not stack. Under the state's storage rules, a battery in the state program cannot also get another New Jersey grant or rebate made for storage. And the proposal takes new batteries only, so a battery you install now likely cannot join later. That is our reading of the proposal, and the final rules may differ.
- Buy now if you need backup soon and you are a PSE&G customer: $5,000 comes off the price today.
- Buy now if you are a JCP&L customer: its program pays a battery you already own.
- Wait if you are on Atlantic City Electric or Rockland Electric and can live without backup until mid-2027.
- Waiting has risks: the proposal can change, and each utility's share is first come, first served.
- Buying now with PSE&G locks you in for 84 months of events.
What does a home battery cost in New Jersey?
The BPU's own cost model uses $1,250 per kWh for a home battery system under 10 kW. For a 13.5 kWh battery, that is about $16,900, by our math. With PSE&G's $5,000 off, that drops to about $11,900.
Quotes vary with the battery, the number of units and the wiring your home needs. Get two or three quotes in writing, and ask each installer whether it is on PSE&G's contractor list if you are a PSE&G customer.
Batteries are still rare here. The BPU staff estimate 8,500 to 11,000 batteries are already in New Jersey homes.
A battery mostly saves money through these programs and backup, not by shifting solar power. New Jersey still credits solar power sent to the grid at the full retail price over a 12-month period. A replacement for that rule is under review.
Will a battery that earns money still back up my home?
Yes, if you keep a reserve. PSE&G keeps 20% of the charge for you during events. JCP&L will not call an event when a severe storm is forecast. Set your own reserve in the battery's app.
Outages are a real worry here. In early July 2026, heat and storms left many New Jersey homes without power for a long time, and the BPU opened a review of how the utilities responded.
- Set a reserve of 20% or more in your battery's app, and raise it before storm season.
- Ask how many events a year the program can call and how long each one lasts.
- Ask which circuits the battery backs up, and whether it can start your central air.
- PSE&G's FAQ says New Jersey's code does not let a home battery send power back to the grid.
- Leaving PSE&G's program before year 5 costs money.
Can I get a battery bundled with my electricity in New Jersey?
No. We found no company selling a home battery bundled with an electricity plan in New Jersey on Oct. 26, 2026. Base Power says it serves homeowners in Texas and Illinois only, although a Base company is on New Jersey's supplier list. Energywell says its battery offers are only in Texas and Illinois.
You can still shop for the power itself. Every home on the four big utilities can pick a supplier. If you plan to join the state battery program, choose a fixed price. The proposal shuts out homes on plans that pass wholesale costs through. Our New Jersey electricity suppliers guide explains what to ask.
How do you claim a New Jersey battery incentive?
Start with your utility, then the program's own page. Most programs sign you up through the installer or the battery maker's app, not a form at the utility.
- Find your utilityYour bill names it at the top: PSE&G, JCP&L, Atlantic City Electric or Rockland Electric.
- Read the program pageCheck the amount, the battery list, the term and what leaving early costs.
- Pick an installerFor PSE&G's discount, use a contractor in its program. It takes the $5,000 off the bill.
- Enroll and set a reserveJoin through the installer or the battery app, and pick how much charge to keep for outages.
- Give the seller Form ST-4If the battery stores solar power, the form can remove New Jersey sales tax.
Keep every paper: the program terms, your enrollment email and the install date. PSE&G's payback rules and the IRS both use dates.
Know which battery program fits you? Next, check your supply price. Compare fixed-price plans at your ZIP against your utility's price to compare.
Compare plans at my ZIPA partner runs the plan finder. If you sign up, it may pay us a fee, and that never moves a rating or a score.
Questions, answered
Does New Jersey have a home battery rebate?
Not statewide yet. On Oct. 26, 2026, PSE&G took $5,000 off a new battery through its GridSmart pilot, and JCP&L paid battery owners about $360 a summer. The state's home battery program is a proposal, planned to open by July 2027.
What is GSESP Phase 2?
It is the second phase of the Garden State Energy Storage Program. It starts with a 150 MW home block that would pay up to $200 per kW a year for 10 years. BPU staff proposed it on Aug. 17, 2026, and it is planned to open by July 2027.
How much would the state program pay me?
In the BPU staff's own example, a 13.5 kWh battery earns about $540 a year, not the $2,300 top rate, because pay is cut for how much power the battery gives during events. Your amount depends on your battery and how it performs.
Can I get PSE&G's $5,000 for a battery I already have?
No. PSE&G's GridSmart program takes new batteries you buy through one of its contractors. It does not take leased batteries or ones already installed.
Can I join both PSE&G's program and the state program?
Likely not. The state program is planned to take new batteries only, and a battery in it cannot also get another New Jersey storage rebate. That is our reading of the Aug. 17, 2026 proposal.
Can I get paid for my Powerwall in New Jersey?
In the JCP&L area, yes: its Energy Saving Rewards program takes Powerwall 2, 3 and + batteries. In the PSE&G, Atlantic City Electric and Rockland Electric areas, we found no program that pays for a battery you already own.
Can I still get the 30% tax credit for a battery?
Not for a new install. The federal credit does not apply to batteries placed in service after Dec. 31, 2025. A battery finished by that date can still be claimed on your 2025 return.
Do I pay sales tax on a home battery in New Jersey?
Maybe not, if it stores solar power. The state exempts solar energy devices, including ones that store solar power. Give the seller Form ST-4. A battery charged only from the grid is not clearly covered.
What do you want to do next?
Sources and updates
Sources (25)
- New Jersey BPU, Garden State Energy Storage Program Phase 2, Block 1: Staff Straw Proposal (Aug. 17, 2026), Docket QO26040116: The 150 MW home block, up to $200 per kW a year for 10 years, the Performance Factor and the $540 example, events, the 73/52/21/4 MW split, new batteries only, the $50 fee, the 70% pass-through, the supplier rule, the timeline, the $1,250 per kWh cost model, the 30% business credit assumption and the 8,500 to 11,000 battery estimate (read Oct. 26, 2026).
- New Jersey BPU, NJBPU Advances Statewide Home Batteries Program (Aug. 19, 2026): The home block proposal and its comment period (read Oct. 26, 2026).
- New Jersey BPU, Order launching the Garden State Energy Storage Program (June 18, 2025): Phase 1 is for large grid batteries and Phase 2 for batteries at homes and businesses (read Oct. 26, 2026).
- New Jersey BPU, Board agenda, Oct. 28, 2026: No home block order on the agenda (read Oct. 26, 2026).
- New Jersey BPU, Board agenda, Oct. 14, 2026: No home block order on the agenda (read Oct. 26, 2026).
- New Jersey BPU, Virtual Power Plant Staff Straw Proposal (July 15, 2026), Docket QO26030099: Proposed programs for batteries people already own, 2027 to 2029, and a staff report on a replacement for net metering expected in 2026 (read Oct. 26, 2026).
- New Jersey Clean Energy Program, Energy storage FAQs: A battery in the state program cannot also get another New Jersey grant or rebate made for storage (read Oct. 26, 2026).
- PSE&G, PSE&G Introduces GridSmart Battery Program (Aug. 26, 2026): The $5,000 incentive and up to $25,000 interest-free on-bill repayment (read Oct. 26, 2026).
- PSE&G, GridSmart customer terms and conditions: 84 months of control, up to 100 events a year of up to 4 hours, the 20% reserve, 1 hour's notice and the year-by-year payback (read Oct. 26, 2026).
- PSE&G, GridSmart FAQs: New bought batteries only through a participating contractor, the smart meter, Wi-Fi and 12-month rules, the battery list, the 8.5 kW wording, limited spots and the no-export code note (read Oct. 26, 2026).
- JCP&L, Energy Saving Rewards for batteries: The $100 per average kW wording, $360 a summer for the average customer, the prepaid Visa, the battery list and no events before severe storms (read Oct. 26, 2026).
- JCP&L, Energy Saving Rewards FAQ: The 6 kW, $360 example, existing batteries and no solar needed (read Oct. 26, 2026).
- JCP&L and EnergyHub, Battery program terms: The program period of June 1, 2025 to June 30, 2027 and leaving any time (read Oct. 26, 2026).
- Atlantic City Electric, Energy Wise Rewards: Smart thermostats only, up to $100 (read Oct. 26, 2026).
- New Jersey BPU, Utility presentations, July 30, 2026 meeting, Docket QO26030099: Rockland Electric listed only a thermostat program for New Jersey homes (read Oct. 26, 2026).
- IRS, Residential Clean Energy Credit: Not available for property placed in service after Dec. 31, 2025 (read Oct. 26, 2026).
- IRS, FAQs on the July 4, 2025 changes to sections 25C, 25D and others (FS-2025-05): The cost counts when the install is finished (read Oct. 26, 2026).
- U.S. Congress, Public Law 119-21, section 70506: Ends the residential clean energy credit for spending after Dec. 31, 2025 (read Oct. 26, 2026).
- New Jersey Division of Taxation, Bulletin S&U-6, Energy: The sales tax exemption for solar energy devices, including storage of solar power, with Form ST-4 (read Oct. 26, 2026).
- New Jersey Division of Taxation, Renewable energy system property tax exemption form (CRES): Lists systems that make power; storage is not listed (read Oct. 26, 2026).
- New Jersey Clean Energy Program, Net metering and interconnection: Full retail credit over a 12-month period for solar power (read Oct. 26, 2026).
- New Jersey BPU, Storm response review, July 2026: The board's review of the utilities' response to the early July 2026 outages (read Oct. 26, 2026).
- New Jersey BPU, NJ Power Switch supplier list: Base Retail, LLC on the list of licensed suppliers (read Oct. 26, 2026).
- Base Power, Home page: Serving homeowners in Texas and Illinois (read Oct. 26, 2026).
- Energywell, Home page: Battery offers only in Texas and Illinois (read Oct. 26, 2026).
Changelog · last updated October 26, 2026 · 1 update
- October 26, 2026: Guide published.
How to cite this page: The Day Company, "New Jersey battery incentives in 2026: what pays now, what opens in 2027, and the catch", updated October 26, 2026, https://theday.company/nj/battery-incentives-new-jersey.
The Day Company is not affiliated with any utility, battery maker, installer or agency named on this page. Program amounts were read on each program's own page or the BPU's filings on Oct. 26, 2026, and programs can change or close without notice. The state program is a staff proposal and may change before it opens. The 10-year figures assume today's amounts stay the same. This guide is information, not tax or legal advice. Our plan finder is Power HQ, operated by Blitz Ventures Inc. (doing business as EnergyBot), which holds New Jersey Board of Public Utilities licence EA-0519.