IllinoisInstallTimelineReviewed

How does solar panel installation work in Illinois, and how long does it take?

Seven steps take you from a signed contract to a working system. Here is each one in order, the time the state and your utility allow, and what you do yourself.

See if solar fits my home →Free · ~60 seconds · No obligation
Published 8 min readBy The Day Company review team · How we verify figures
7steps from contract to switch-on
22 business daysstate clock for a complete home review
The short answer

Solar installation in Illinois takes 7 steps. The utility has 22 business days to review a complete home application. Your installer files most of the papers. The roof work is the short part. You cannot switch on until ComEd or Ameren gives written permission to operate.

What do you need right now?
Check my eligibility →

The Day Company is an independent solar, battery and electricity information resource. Information you submit may be used by our review team and authorized partners to contact you about your request.

Do not switch on early. Under ComEd's September 2026 rules, a system turned on with no written yes will be disconnected. That means ComEd cuts it off the grid. Wait for the signed approval.
7steps from contract to switch-on
22 business daysstate clock for a complete home review
up to 10 business daysfinal utility hookup after inspection
18 monthsinstaller deadline after the state contract

The 3 things to know

  • You sign. Your installer, or a company it works with, files. Only a state-approved company can file Illinois Shines.
  • The utility step is the long wait. ComEd and Ameren get 22 business days on a complete home file. A missing page can add 10 more.
  • Two lists do two jobs. The Illinois Commerce Commission certifies installers. A different list names who may file the state form. Check both.

Built on public data from: the Illinois Power Agency (Illinois Shines), the Illinois Commerce Commission, ComEd and Ameren Illinois's own interconnection guides, and the University of Illinois Extension.

Independent public sources we cite and link — The Day Company is not affiliated with or endorsed by any of them.

On this page
01 · The steps

What are the steps, in order?

Illinois Shines is the state solar program. These are its steps, set next to the utility steps.

A disclosure form is the state paper you sign before the contract. It lists the price, the deposit, the warranties, and the dates.

  1. Sign the disclosure, then the contractYou get the form and a brochure first. The state filing cannot start until you sign.
  2. Design and permitThe installer designs the system and files the city or county permit. A homeowners association may have to approve it too.
  3. State form (Part I)The installer files Part I and has 14 days to fix errors. The Illinois Commerce Commission approves batches about 2 weeks apart.
  4. Utility formThe installer files with ComEd or Ameren. A normal home uses Level 1, with a $50 fee.
  5. InstallThe crew mounts the panels and the inverter. The disclosure form lists the start and finish dates.
  6. Inspection and testYour city or county inspects. Ameren runs a test visit. ComEd asks for inverter photos, inspection proof, and the drawings.
  7. Permission to operateThe utility signs off in writing. Then you switch on. Credits start within 1 to 2 months.

Level 1 is the expedited home track. Expedited means a set clock. An inverter turns panel power into home power. Permission to operate is the written yes to switch on.

After switch-on, the installer sends Part II. That form proves the system works. The state pays the installer, not you. On a system of 25 kW or less, 50% is paid up front, and the rest is paid quarterly over six years. See the Illinois Shines guide.

The steps overlap. File the utility form when the design is done. Do not wait for the roof work.

02 · The clocks

How long does each step take?

The state sets some of these times by rule. Your utility sets others. Some steps have no published time. The table says which. We read these sources on November 10, 2026.

Published times for a standard Illinois home system
StepTime allowedWho sets it
Utility says your file is complete7 business daysIllinois Commerce Commission rule
You fix missing information10 business days, or the request is droppedIllinois Commerce Commission rule
Utility checks your design15 business days after completeIllinois Commerce Commission rule
You sign the utility agreement30 business days, then it is droppedIllinois Commerce Commission rule
Ameren Illinois test visitWithin 15 business days of your done noticeAmeren Illinois guide, June 2023
Ameren Illinois permission to operateUsually 2 business days after the testAmeren Illinois guide, June 2023
Final hookup after inspectionTypically up to 10 business daysUniversity of Illinois Extension
ComEd permission to operateNo time publishedComEd requirements, September 2026
Illinois Shines Part I errors14 days to fixIllinois Shines
State contract signedOne to two weeks after approval, then 7 business daysIllinois Shines
Finish the installUp to 18 months after approvalIllinois Shines
Design and city permitNo time published. Ask your installer and your cityLocal rules

Add 7 days to 15 days. You get 22 business days. That is about four and a half weeks. It is the longest review on a complete file. A missing page adds a 10-day fix window. The wait can then reach 32 business days.

Three tests keep a home on this track. It sends 25 kW or less. It is 50 kW or less in total. The inverter is lab-certified. That means a test lab approved the gear.

How the state review clock adds up
Say the file is complete
7 days
Check the design
15 days
Full review, no fix
22 days
Review plus a fix
32 days

Business days from Illinois Commerce Commission rules. The full review adds the first two bars.

A late filing costs you the most time. Some installers send the utility form only after the install. The whole review then sits at the end. The panels sit idle. Ask when they file.

03 · Your dates

Plan your own dates

Type the day you plan to sign. Type the times your installer quotes for design, permit, and inspection. The planner adds the published utility times. It shows when you could switch on.

Plan your solar install dates

Type the dates your installer quotes. The tool adds the review times the state and your utility publish, and shows when you could switch on.

This is a planning aid built from the published limits in the table above. Your installer and utility set the real dates, and weekends are the only days it skips.

04 · Fees

What fees show up along the way?

Most of your cost is the system itself. Our cost guide covers that. These are the smaller fees tied to the steps.

Fees tied to the install steps
FeeAmountWhere it comes from
Utility form for a standard home system50ComEd and Ameren Illinois guides
Most you can be billed for the Level 1 hookup$200 cap. Costs above it go into delivery ratesIllinois Commerce Commission rule
Optional report on your circuit, before you apply$300 at ComEdComEd requirements, September 2026
Illinois Shines form feeMust be shown on your disclosure formIllinois Shines
City or county permitVaries. Chicago lists its ownChicago solar permits

If a quote lists $200 as the form fee, ask why. That amount is a cost cap. The form fee in the guides is $50.

05 · Your part

What do you do, and what does your installer do?

The installer files. An approved vendor is a company the state lets file Illinois Shines. Your own list is short.

  • Read and sign the disclosure form before the contract. It lists price, deposit, warranties, and the planned dates.
  • Pick the installer. Check the Illinois Commerce Commission certified list and the Illinois Shines approved-vendor list.
  • Let the inspector in. Illinois Shines inspects a random share of projects at no cost to you. You may decline.
  • Ask for written proof that net metering is set up. That is the bill credit for power you send back. See ComEd and Ameren.
  • Do not file the Illinois Shines form. Only an approved vendor can.
  • Do not switch the system on before the utility says yes.
  • Do not climb on the roof for an inspection. The program tells customers not to.
06 · DIY

Can you install solar panels yourself in Illinois?

Sometimes, but it is hard. A self-installer puts the system on their own land and takes no help. The utility needs your written statement that you are one before net metering.

Anyone else who connects it must be certified by the Illinois Commerce Commission. A friend does not count. An uncertified electrician does not count.

The city still permits and inspects. The utility still reviews the design. Illinois Shines still needs an approved vendor, or you may lose the state credit money. Ameren Illinois says solar is not a do-it-yourself project. We could not confirm a vendor will file for a system you built. Call (877) 783-1820 before you buy parts.

07 · Delays

What slows an install down?

Most delays are paperwork, not roof work.

  • A late or incomplete utility form. A missing page can add 10 business days before the 15-day check starts.
  • Waiting on the state contract. Some installers wait for it before they start. Ask if yours does.
  • A roof that needs work first. Taking panels off to re-roof costs money. The Illinois Solar Energy and Storage Association suggests at least 15 years of life left.
  • An HOA review. A homeowners association cannot ban panels, but it can slow the plan. See what an Illinois HOA can require.
  • Inspection scheduling. See Chicago and Aurora.
08 · Your roof

Is your home ready for these steps?

Solar is a poor fit on some homes. Know that before you sign.

Roof lifeAim for at least 15 years left. Re-roof first if you are close.
Midday shadeShade at midday cuts power. Measure it. Do not guess.
Who owns itYou cannot put panels on a home you do not own.

See roof needs, shaded roofs, community solar, and selling a house with solar.

The free check looks at roof, shade, and usage. Prices are in what solar costs in Illinois.

09 · The quote

What should I check before I sign?

Treat the disclosure form as the quote check. Price, deposit, warranties, and dates should be on it. So should the Illinois Shines dollars in your price.

  • The utility fee is $50, not the $200 cap.
  • Ask, in writing, how many credit dollars are in the price.
  • The utility form waits until after the roof work.

What to demand is in how to vet a solar quote.

10 · The installer

Who should install it?

Check the Illinois Commerce Commission list, the Illinois Shines approved-vendor list, and the complaint reports. The steps are in how to verify a vendor. We do not rank installers on this page.

Your next step

Use the free check to see if your roof and bill make solar a fit before you sign a contract.

Read nextWhat does Illinois Shines pay, and who gets it? Read it
11 · Quick answers

Questions, answered

How long does it take to install solar panels in Illinois?

Roof work is the short part. Utility review can take 22 business days. Then add the permit, the inspection, and the hookup.

Do you need a permit to install solar panels in Illinois?

Most cities and counties require one. Fees vary. See Chicago solar permits and Aurora solar permits.

Is it worth installing solar panels in Illinois?

It can be if you own the roof and ComEd or Ameren delivers power. The roof, your use, and the deal decide it. See the math in is solar worth it in Illinois.

What is the typical cost of installing solar panels in Illinois?

About $34,000 to $35,000 for a typical 9.4 kW system, before incentives. The 30% federal homeowner credit ended after December 31, 2025. Do not subtract it. See solar panel cost in Illinois.

Is the state of Illinois paying for solar panels?

No check comes to you. Illinois Shines pays your installer, who may lower your price. ComEd and Ameren pay a rebate too. Lower-income homes can use Illinois Solar for All. See ComEd's solar rebate.

What is the 33% rule in solar panels?

It is a fire-code limit on how much of the roof panels may cover. Wider walkways are needed past that share. Local code sets it. We found no Illinois statewide rule.

Why are people getting rid of their solar panels?

A new roof is the usual reason. You pay to take the panels off and put them back. Check roof age before you sign.

Who files the ComEd or Ameren application?

Your installer, in most cases. ComEd wants its online portal. Ameren Illinois uses PowerClerk. The home-system fee is $50.

When do bill credits start after install?

1 to 2 months after net metering is set up, Illinois Shines says.

Where to next

What do you want to do next?

Check that your roof can take the seven steps.

See in about a minute if solar fits your roof. It's free, and if it's not a fit, it says so.

Free eligibility check · ComEd & Ameren · No obligation

The Day Company is an independent solar, battery and electricity information resource. Information you submit may be used by our review team and authorized partners to contact you about your request. Checking eligibility creates no obligation.

Sources

Sources and updates

Sources (12)
Changelog · 3 updates, newest November 10, 2026
  • November 10, 2026: Added links to related guides. Re-checked every fact; changed the payment line from "50% is paid when it is energized" to "50% is paid up front, the rest paid quarterly over six years" (Illinois Shines Project Status says "upfront" and does not tie it to switch-on), and fixed a doubled percent sign.
  • November 9, 2026: Rebuilt for easier reading: shorter sentences, a review-clock chart, and the same steps, fees, and clocks.
  • October 25, 2026: Guide published.

How to cite this page: The Day Company, "How does solar panel installation work in Illinois, and how long does it take?", updated November 10, 2026, https://theday.company/answers/solar-panel-installation-illinois.