How does solar panel installation work in Illinois, and how long does it take?

Seven steps take you from a signed contract to a working system. Here is each one in order, the time the state and your utility allow, and what you do yourself.

See if solar fits my home →Free · ~60 seconds · No obligation
Published 10 min readBy The Day Company review team · How we verify figures
7steps from contract to switch-on
22 business daysthe state's clock for a utility to review a complete home application
The short answer

Solar installation in Illinois takes seven steps, and your installer files most of the paperwork. The roof work is the short part. The waiting is in the permit and the ComEd or Ameren Illinois review, and you cannot switch on until your utility gives written permission to operate.

What do you need right now?
Check my eligibility →

The Day Company is an independent solar, battery and electricity information resource. Information you submit may be used by our review team and authorized partners to contact you about your request.

Do not switch on early. ComEd's September 2026 rules say equipment turned on without permission to operate will be disconnected from its grid. Wait for the signed approval.
7steps from contract to switch-on
22 business daysthe state's clock for a utility to review a complete home application
up to 10 business daysfor the final utility hookup after inspection, per Illinois Extension
18 monthsthe installer's deadline to finish after the state contract

The 3 things to know

  • Your installer files, you sign. Only a state-approved company can file the Illinois Shines application. Your installer, or a partner of it, files the permit and the utility application too.
  • The utility step is the long one. The state gives ComEd and Ameren 22 business days to review a complete home application. A missing page can add 10 more.
  • Two lists, two jobs. An installer must be certified by the Illinois Commerce Commission. The company that files the state application is a different list. Check both.

Built on public data from: the Illinois Power Agency (Illinois Shines), the Illinois Commerce Commission, ComEd and Ameren Illinois's own interconnection guides, and the University of Illinois Extension.

Independent public sources we cite and link — The Day Company is not affiliated with or endorsed by any of them.

On this page
01 · The steps

What are the steps, in order?

Illinois Shines, the state solar program, lists its own steps. We put them next to the utility's steps, so you can see the whole path in one place.

  1. Sign the disclosure form, then the contractThe installer must give you a state disclosure form and brochure first. It cannot start the state application until you sign the form
  2. Design and permitThe installer designs the system and files the city or county permit. A homeowners association may need to approve it too
  3. State application (Illinois Shines Part I)The installer files it and has 14 days to fix errors. The Illinois Commerce Commission approves batches about every 2 weeks
  4. Utility applicationThe installer files with ComEd or Ameren Illinois. A normal home system uses the fastest track, called Level 1, with a $50 fee
  5. InstallThe crew mounts the panels and inverter. Your disclosure form lists the planned start and finish dates
  6. Inspection and testYour city or county inspects. Ameren runs a test visit. ComEd asks for photos of the inverter labels, the inspection proof and the as-built drawings
  7. Permission to operateYour utility signs off in writing. Then you switch on, and bill credits start within 1 to 2 months. Extension says the final hookup typically takes up to 10 business days after inspection

After switch-on, your installer sends the state a second form, called Part II, to prove the system works. The state then pays the installer, not you. For a system of 25 kW or less, half of that money comes when the system is energized. Our Illinois Shines guide shows what it pays and how to make sure it lowers your price.

The seven steps overlap. A good installer files the utility application as soon as the design is done, and does not wait for the roof work.

02 · The clocks

How long does each step take?

The state sets some of these times by rule. Your utility sets others in its own guide. Some steps have no published time at all, and the table says so. We read every source on October 25, 2026.

Published times for a standard Illinois home system
StepTime allowedWho sets it
Utility says your application is complete7 business daysIllinois Commerce Commission rule
You fix missing information10 business days, or the request is droppedIllinois Commerce Commission rule
Utility checks your design15 business days after "complete"Illinois Commerce Commission rule
You sign the utility agreement30 business days, then it is droppedIllinois Commerce Commission rule
Ameren Illinois test visitWithin 15 business days of your "done" noticeAmeren Illinois guide, June 2023
Ameren Illinois permission to operateUsually 2 business days after the testAmeren Illinois guide, June 2023
Final hookup after inspectionTypically up to 10 business daysUniversity of Illinois Extension
ComEd permission to operateNo time publishedComEd requirements, September 2026
Illinois Shines Part I errors14 days to fixIllinois Shines
State contract signed1 to 2 weeks after approval, then the installer has 7 business daysIllinois Shines
Finish the installUp to 18 months after approvalIllinois Shines
Design and city permitNo time published. Ask your installer and your cityLocal rules

Add the 7 days to the 15 days and you get 22 business days, about four and a half weeks. That is the longest the state lets a utility take on a complete home application. If the application is missing something, the 10-day fix window can push it to 32. A home system gets this fast track when it sends 25 kW or less to the grid, is 50 kW or less in all, and uses an inverter with lab-certified equipment.

A late filing costs you the most. Some installers send the utility application only after the install. That puts the whole review at the end, and the panels sit idle. Ask when they file.

03 · Your dates

Plan your own dates

Type the day you plan to sign, and the times your installer quotes for design, permit and inspection. The planner adds the published utility times and shows when you could switch on.

Plan your solar install dates

Type the dates your installer quotes. The tool adds the review times the state and your utility publish, and shows when you could switch on.

This is a planning aid built from the published limits in the table above. Your installer and utility set the real dates, and weekends are the only days it skips.

04 · Fees

What fees show up along the way?

Most of your cost is the system itself, which our cost guide covers. These are the smaller fees tied to the steps.

Fees tied to the install steps
FeeAmountWhere it comes from
Utility application for a standard home system$50ComEd and Ameren Illinois guides
Most you can be billed for the Level 1 hookup$200 cap. Costs above it go into delivery ratesIllinois Commerce Commission rule
Optional report on your circuit, before you apply$300 at ComEdComEd requirements, September 2026
Illinois Shines application feeMust be shown on your Disclosure FormIllinois Shines
City or county permitVaries. Chicago lists its ownChicago solar permits

If a quote lists $200 as your utility application fee, ask why. The $200 is a cost cap, not the application fee.

05 · Your part

What do you do, and what does your installer do?

The installer does the filing. You do a few things only you can do.

  • You read and sign the state disclosure form before the contract. It lists the full price, the deposit, the warranties and the estimated start and finish dates.
  • You pick the installer. Check the Illinois Commerce Commission list of certified installers and the Illinois Shines list of approved vendors.
  • You let the inspector in. Illinois Shines inspects a random share of projects at no cost to you. You may decline.
  • You ask for written proof that net metering is set up, so credits start on your bill.
  • You do not file the Illinois Shines application. Only an approved vendor can.
  • You do not switch the system on before the utility says yes.
  • You do not climb on the roof for any inspection. The program tells customers not to.
06 · DIY

Can you install solar panels yourself in Illinois?

Sometimes, but it is hard. Illinois law has a "self-installer": a person who buys or leases a system for their own use and puts it in on their own property with no help from anyone else. Your utility needs your written statement that you are one before it will give you net metering.

Everyone else who connects the system must be certified by the Illinois Commerce Commission. A friend or an uncertified electrician does not count, and a self-installer cannot have help.

Three things still apply. Your city or county still needs a permit and an inspection. The utility still reviews the design and sets the switch-on. And the Illinois Shines application must come from an approved vendor, so you may lose the state's solar credit money. Ameren Illinois's own solar page calls solar "not a DIY project." We could not confirm whether a vendor will file for a system you built, so call Illinois Shines at (877) 783-1820 before you buy parts.

07 · Delays

What slows an install down?

Most delays are paperwork, not roof work.

  • A late or incomplete utility application. A missing page can add 10 business days before the 15-day check even starts.
  • Waiting on the state contract. Some installers wait for it before they start. Ask if yours does.
  • A roof that needs repair first. Panels outlast a worn roof, and taking them off to re-roof is costly. The Illinois Solar Energy and Storage Association suggests a roof with at least 15 years left.
  • An HOA review. It cannot ban panels, but it can slow the plan. See what an Illinois HOA can require.
  • Inspection scheduling. Cities set their own pace. Chicago and Aurora publish theirs: Chicago, Aurora.
08 · Your roof

Is your home ready for these seven steps?

Solar is a poor fit in some homes, and it is better to know before you sign. Be careful if:

  • Your roof is within about 10 years of a replacement. Re-roof first, or the panels will have to come off and go back on. See Illinois roof requirements.
  • Shade covers the roof in the middle of the day. Measured shade decides this, not guesses. See solar on a shaded roof.
  • You rent, or live in a building you do not own. You cannot put panels on it. Community solar is the option to read.
  • You may move within a few years. Read selling a house with solar first.

If none of those apply, the free solar check looks at your roof, shade and usage and tells you if solar fits. When it does not fit, it says so. For the cost side, see what solar costs in Illinois.

09 · The installer

Who should install it?

Check any company the same way. Do three lookups before you sign: the Illinois Commerce Commission list of certified installers, the Illinois Shines approved vendor list, and the program's complaints and violations reports. We explain each lookup in how to verify a vendor, and what to ask in is my quote a good deal. We do not rank installers on this page.

10 · Quick answers

Questions, answered

How long does it take to install solar panels in Illinois?

The roof work is short, and your disclosure form lists the planned dates. Start to finish takes longer, because the utility review alone can take 22 business days under state rules, plus the permit, the inspection and the final hookup. The planner above adds up your own dates.

Do you need a permit to install solar panels in Illinois?

Almost always, from your city or county. Rules and fees vary. We cover two big ones in our guides to Chicago solar permits and Aurora solar permits.

Is it worth installing solar panels in Illinois?

For many owner-occupied ComEd and Ameren homes, yes, but it depends on your roof, your use and the deal. We lay out the math in is solar worth it in Illinois.

What is the typical cost of installing solar panels in Illinois?

Our cost guide puts a typical 9.4 kW home system at about $34,000 to $35,000 before incentives in 2026. See the current figures in solar panel cost in Illinois.

Is the state of Illinois paying for solar panels?

Not directly. Illinois Shines pays your installer for the solar credits your system makes, and the installer may pass some of that on as a lower price. ComEd and Ameren also pay a rebate, and income-eligible homes can use Illinois Solar for All. See ComEd's solar rebate.

What is the 33% rule in solar panels?

It usually means a fire-code limit on how much of the roof panels may cover before wider walkways are needed. It is set by local code, and we found no Illinois statewide roof-coverage rule. Ask your city's permit office.

Why are people getting rid of their solar panels?

The common reason is a roof replacement, which means paying to take the panels off and put them back. Moves and leased systems are others. That is why roof age matters before you sign.

Who files the ComEd or Ameren application?

Your installer, in most cases. ComEd urges applicants to use its online portal, and Ameren Illinois uses PowerClerk. Both list a $50 fee for a standard home system.

When do bill credits start after install?

Illinois Shines says credits generally show up within 1 to 2 months of net metering being set up.

Next: the money sideWhat does Illinois Shines pay, and who gets it? Read it
Where to next

What do you want to do next?

Check that your roof can take the seven steps.

See in about a minute if solar fits your roof. It's free, and if it's not a fit, it says so.

Free eligibility check · ComEd & Ameren · No obligation

The Day Company is an independent solar, battery and electricity information resource. Information you submit may be used by our review team and authorized partners to contact you about your request. Checking eligibility creates no obligation.

Sources

Sources and updates

Sources (12)
Changelog · last updated October 25, 2026 · 1 update
  • October 25, 2026: Guide published.